Construction of the first phase of a new facility is complete. The four-story building has 112,000 square feet of space. A ribbon cutting ceremony is scheduled for September 25.

Patients are expected to be seen starting in early October. The project was nearing completion in February, with about 75% of construction finished at that time. A temporary certificate of occupancy was received in June, allowing some staff to begin working inside.

Further details about the facility and its opening are available. The new building is part of Mount Sinai Medical Center's expansion.